Green Island Logistics Center: proposed parcel and building changes

Based on 5 sources · most recently checked Oct 13, 2026 · See how we know

Green Island Road at Highway 29

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved.

The proposed changes

  • Lot 2 modification: replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park.
  • Lot line adjustment: move an interior parcel line to create a separate lot for Building B.

Background

Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic.

The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions.

What we don't know

We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

Share this story

Select story link

How we know (5 sources)

Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.

Supporting source

The city’s September 2026 inventory lists two changes proposed for Green Island Logistics Center, formerly called Giovannoni Logistics: a parcel adjustment for Building B and a modification replacing three buildings on Lot 2 with two. The modification describes a change from 503,050 to 471,332 square feet; those figures concern the proposed Lot 2 layout, not the entire logistics park. Buzz Oates identifies the larger project at Green Island Road and Highway 29 in American Canyon. These application entries do not establish approval of the changes or current construction. The saved September inventory could not be refreshed during this review.

American Canyon September 2026 development inventory

City of American Canyon · pdf:p1:table1:r4; pdf:p2:table1:r2

Evidence dated: Date not stated · Source checked: Oct 6, 2026

Owner-authorized agent evidence review under #24. Parent update is attributed and dated; current outcomes and forecasts are not inferred. No human reviewer impersonated.

Supporting source

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved. ## The proposed changes - **Lot 2 modification:** replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park. - **Lot line adjustment:** move an interior parcel line to create a separate lot for Building B. ## Background Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic. The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions. ## What we don't know We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

American Canyon looking at big proposed industrial development

Napa Valley Register · 2022 background by Barry Eberling: acreage, square footage, phases, review objections

Evidence dated: Nov 18, 2022 · Source checked: Oct 13, 2026

Owner-authorized agent review of readable source content on October 13, 2026. Used only for the added context sentence it supports; dates and outcomes stay distinguished from forecasts.

Supporting source

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved. ## The proposed changes - **Lot 2 modification:** replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park. - **Lot line adjustment:** move an interior parcel line to create a separate lot for Building B. ## Background Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic. The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions. ## What we don't know We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

Active planning projects, September 2026

City of American Canyon · Page 6, row 6: 70.2-acre mass grading on hold since Oct 2024

Evidence dated: Sep 1, 2026 · Source checked: Oct 13, 2026

Owner-authorized agent review of readable source content on October 13, 2026. Used only for the added context sentence it supports; dates and outcomes stay distinguished from forecasts.

Supporting source

Buzz Oates identifies Green Island Logistics Center at Green Island Road and Highway 29, American Canyon. Its park-wide portfolio does not establish approval or completion of the proposed Lot 2 modification.

Green Island Logistics Center

Buzz Oates · Green Island section

Evidence dated: Date not stated · Source checked: Oct 7, 2026

Exact-site/source-family context manually read during owner-authorized #24 evidence review; does not establish unsupported outcomes.

Summary

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved. ## The proposed changes - **Lot 2 modification:** replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park. - **Lot line adjustment:** move an interior parcel line to create a separate lot for Building B. ## Background Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic. The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions. ## What we don't know We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

American Canyon September 2026 development inventory

City of American Canyon · pdf:p1:table1:r4; pdf:p2:table1:r2

Evidence dated: Date not stated · Source checked: Oct 6, 2026

Owner-authorized agent editorial review (issue #120). The story was reorganized into sections and plain-language wording from this previously reviewed source. Added context sentences are supported by the supporting_source entries dated October 13, 2026.

American Canyon / Industry

Updated

Green Island Logistics Center: proposed parcel and building changes

Based on 5 sources · most recently checked Oct 13, 2026 · See how we know

Green Island Road at Highway 29

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved.

The proposed changes

  • Lot 2 modification: replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park.
  • Lot line adjustment: move an interior parcel line to create a separate lot for Building B.

Background

Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic.

The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions.

What we don't know

We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

Share this story

Select story link

How we know (5 sources)

Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.

Supporting source

The city’s September 2026 inventory lists two changes proposed for Green Island Logistics Center, formerly called Giovannoni Logistics: a parcel adjustment for Building B and a modification replacing three buildings on Lot 2 with two. The modification describes a change from 503,050 to 471,332 square feet; those figures concern the proposed Lot 2 layout, not the entire logistics park. Buzz Oates identifies the larger project at Green Island Road and Highway 29 in American Canyon. These application entries do not establish approval of the changes or current construction. The saved September inventory could not be refreshed during this review.

American Canyon September 2026 development inventory

City of American Canyon · pdf:p1:table1:r4; pdf:p2:table1:r2

Evidence dated: Date not stated · Source checked: Oct 6, 2026

Owner-authorized agent evidence review under #24. Parent update is attributed and dated; current outcomes and forecasts are not inferred. No human reviewer impersonated.

Supporting source

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved. ## The proposed changes - **Lot 2 modification:** replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park. - **Lot line adjustment:** move an interior parcel line to create a separate lot for Building B. ## Background Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic. The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions. ## What we don't know We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

American Canyon looking at big proposed industrial development

Napa Valley Register · 2022 background by Barry Eberling: acreage, square footage, phases, review objections

Evidence dated: Nov 18, 2022 · Source checked: Oct 13, 2026

Owner-authorized agent review of readable source content on October 13, 2026. Used only for the added context sentence it supports; dates and outcomes stay distinguished from forecasts.

Supporting source

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved. ## The proposed changes - **Lot 2 modification:** replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park. - **Lot line adjustment:** move an interior parcel line to create a separate lot for Building B. ## Background Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic. The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions. ## What we don't know We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

Active planning projects, September 2026

City of American Canyon · Page 6, row 6: 70.2-acre mass grading on hold since Oct 2024

Evidence dated: Sep 1, 2026 · Source checked: Oct 13, 2026

Owner-authorized agent review of readable source content on October 13, 2026. Used only for the added context sentence it supports; dates and outcomes stay distinguished from forecasts.

Supporting source

Buzz Oates identifies Green Island Logistics Center at Green Island Road and Highway 29, American Canyon. Its park-wide portfolio does not establish approval or completion of the proposed Lot 2 modification.

Green Island Logistics Center

Buzz Oates · Green Island section

Evidence dated: Date not stated · Source checked: Oct 7, 2026

Exact-site/source-family context manually read during owner-authorized #24 evidence review; does not establish unsupported outcomes.

Summary

Green Island Logistics Center, formerly called Giovannoni Logistics, is a warehouse and industrial park at Green Island Road and Highway 29 in American Canyon. The city's September 2026 inventory lists two proposed changes from the developer, Buzz Oates. Neither is shown as approved. ## The proposed changes - **Lot 2 modification:** replace three buildings (503,050 square feet) with two (471,332 square feet). Those figures cover Lot 2 only, not the whole park. - **Lot line adjustment:** move an interior parcel line to create a separate lot for Building B. ## Background Barry Eberling reported in the Napa Valley Register on November 18, 2022 that Buzz Oates proposed a 208-acre project near Green Island and Devlin roads. It would have about 2.4 million square feet of warehouses, built in two phases. The Center for Biological Diversity said the plan did not do enough to offset the loss of wildlife habitat. Others questioned the environmental review and traffic. The city's list also shows a mass-grading application for 70.2 acres of the project. In October 2024, the applicant put it on hold, citing market conditions. ## What we don't know We have not confirmed approval of either change or any current construction. The 2022 report predates the current proposals, and the city list is from September.

American Canyon September 2026 development inventory

City of American Canyon · pdf:p1:table1:r4; pdf:p2:table1:r2

Evidence dated: Date not stated · Source checked: Oct 6, 2026