Joe Henderson roofing, flooring and building-removal update
See the dated update below for the reported milestone and timing.
Source: Benicia Unified School District, August 2026 facilities update · checked Oct 5, 2026 · Coverage updated Oct 7, 2026
WhereLocation not yet established
In its August 7, 2026 update, Benicia Unified reported Joe Henderson Elementary’s classroom-wing roofing and selected flooring work completed, the F-3 building removed and asphalt patched. Fencing was still being installed at that time. The district update therefore describes completed campus improvements alongside remaining fencing work; it gives no finish date for that remaining work.
How we know (2 sources)
Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.
Summary
Benicia Unified's August 7 update reports classroom-wing roofing and selected flooring work completed, the F-3 building removed and asphalt patched. Fencing was still being installed. These are campus improvements, not closure of Joe Henderson Elementary; the source does not establish an exact completion date or that the remaining fencing is now finished.
August 2026 facilities updateBenicia Unified School District · busd:joe-henderson / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Summary
In its August 7, 2026 update, Benicia Unified reported Joe Henderson Elementary’s classroom-wing roofing and selected flooring work completed, the F-3 building removed and asphalt patched. Fencing was still being installed at that time. The district update therefore describes completed campus improvements alongside remaining fencing work; it gives no finish date for that remaining work.
August 2026 facilities updateBenicia Unified School District · busd:joe-henderson / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Owner-authorized wording review: state the supported dated milestone or attributed forecast and narrow uncertainty to the specific unsupported outcome. Wording correction based on retained approved source review; no new source fetch claimed.
Benicia / Schools
UnknownAs reported Aug 7, 2026
Joe Henderson roofing, flooring and building-removal update
See the dated update below for the reported milestone and timing.
Source: Benicia Unified School District, August 2026 facilities update · checked Oct 5, 2026 · Coverage updated Oct 7, 2026
WhereLocation not yet established
In its August 7, 2026 update, Benicia Unified reported Joe Henderson Elementary’s classroom-wing roofing and selected flooring work completed, the F-3 building removed and asphalt patched. Fencing was still being installed at that time. The district update therefore describes completed campus improvements alongside remaining fencing work; it gives no finish date for that remaining work.
How we know (2 sources)
Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.
Summary
Benicia Unified's August 7 update reports classroom-wing roofing and selected flooring work completed, the F-3 building removed and asphalt patched. Fencing was still being installed. These are campus improvements, not closure of Joe Henderson Elementary; the source does not establish an exact completion date or that the remaining fencing is now finished.
August 2026 facilities updateBenicia Unified School District · busd:joe-henderson / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Summary
In its August 7, 2026 update, Benicia Unified reported Joe Henderson Elementary’s classroom-wing roofing and selected flooring work completed, the F-3 building removed and asphalt patched. Fencing was still being installed at that time. The district update therefore describes completed campus improvements alongside remaining fencing work; it gives no finish date for that remaining work.
August 2026 facilities updateBenicia Unified School District · busd:joe-henderson / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Owner-authorized wording review: state the supported dated milestone or attributed forecast and narrow uncertainty to the specific unsupported outcome. Wording correction based on retained approved source review; no new source fetch claimed.