ProposedAs reported Aug 7, 2026
Mary Farmar plans replacement classrooms
Proposed, per Benicia Unified School District.
Source: Benicia Unified School District, August 2026 facilities update · checked Oct 5, 2026 · Coverage updated Oct 5, 2026
WhereLocation not yet established
Benicia Unified's August 7 update describes plans to remove five portables and add six classrooms at Mary Farmar, plus lighting, restroom and ceiling upgrades. It forecasts bidding in early 2027 and construction the following summer. These are planning forecasts; contract award and implementation have not been established.
How we know (2 sources)
Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.
Summary
Benicia Unified's August 7 update describes plans to remove five portables and add six classrooms at Mary Farmar, plus lighting, restroom and ceiling upgrades. It forecasts bidding in early 2027 and construction the following summer. These are planning forecasts; contract award and implementation have not been established.
August 2026 facilities updateBenicia Unified School District · busd:mary-farmar / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Development status
Benicia Unified's August 7 update describes plans to remove five portables and add six classrooms at Mary Farmar, plus lighting, restroom and ceiling upgrades. It forecasts bidding in early 2027 and construction the following summer. These are planning forecasts; contract award and implementation have not been established.
August 2026 facilities updateBenicia Unified School District · busd:mary-farmar / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Benicia / Schools
ProposedAs reported Aug 7, 2026
Mary Farmar plans replacement classrooms
Proposed, per Benicia Unified School District.
Source: Benicia Unified School District, August 2026 facilities update · checked Oct 5, 2026 · Coverage updated Oct 5, 2026
WhereLocation not yet established
Benicia Unified's August 7 update describes plans to remove five portables and add six classrooms at Mary Farmar, plus lighting, restroom and ceiling upgrades. It forecasts bidding in early 2027 and construction the following summer. These are planning forecasts; contract award and implementation have not been established.
How we know (2 sources)
Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.
Summary
Benicia Unified's August 7 update describes plans to remove five portables and add six classrooms at Mary Farmar, plus lighting, restroom and ceiling upgrades. It forecasts bidding in early 2027 and construction the following summer. These are planning forecasts; contract award and implementation have not been established.
August 2026 facilities updateBenicia Unified School District · busd:mary-farmar / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Development status
Benicia Unified's August 7 update describes plans to remove five portables and add six classrooms at Mary Farmar, plus lighting, restroom and ceiling upgrades. It forecasts bidding in early 2027 and construction the following summer. These are planning forecasts; contract award and implementation have not been established.
August 2026 facilities updateBenicia Unified School District · busd:mary-farmar / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.