Listed under construction by Benicia Unified School District; see the source date.
Benicia High's performing-arts building is being expanded and renovated, Benicia Unified reported in its August 7, 2026 facilities update. The work has begun. The district expects phased completion by May 2028.
The schedule has shifted. The district's June 2026 update forecast completion by December 2027 and said the venue would close during the work. Phase-specific dates and current venue access are unconfirmed.
This is a facilities project, not a closure of Benicia High School.
How we know (4 sources)
Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.
Supporting source
The June district newsletter forecast performing-arts work completion by December 2027 and said the venue would close for the duration of work.
June 2026 facilities updateBenicia Unified School District · Measure C facilities / BHS
Evidence dated: Jun 5, 2026 · Source checked: Oct 5, 2026
Earlier forecast preserved and distinguished from the August phased-completion forecast.
Supporting source
In its August 7 facilities update, Benicia Unified reports the performing-arts building expansion and renovation have begun, with phased completion anticipated by May 2028. June's update forecast completion by December 2027 and said the venue would close during work. The later forecast differs from the earlier schedule; phase-specific dates and current venue access remain unconfirmed. This is a facilities update, not closure of Benicia High School.
August 2026 facilities updateBenicia Unified School District · busd:benicia-high / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Development status
In its August 7 facilities update, Benicia Unified reports the performing-arts building expansion and renovation have begun, with phased completion anticipated by May 2028. June's update forecast completion by December 2027 and said the venue would close during work. The later forecast differs from the earlier schedule; phase-specific dates and current venue access remain unconfirmed. This is a facilities update, not closure of Benicia High School.
August 2026 facilities updateBenicia Unified School District · busd:benicia-high / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Reviewed district facilities statement as of August 7; implementation, forecasts and unknown dates remain distinct. CDS mapping remains pending.
Summary
Benicia High's performing-arts building is being expanded and renovated, Benicia Unified reported in its August 7, 2026 facilities update. The work has begun. The district expects phased completion by May 2028.
The schedule has shifted. The district's June 2026 update forecast completion by December 2027 and said the venue would close during the work. Phase-specific dates and current venue access are unconfirmed.
This is a facilities project, not a closure of Benicia High School.
August 2026 facilities updateBenicia Unified School District · busd:benicia-high / August facilities section
Evidence dated: Aug 7, 2026 · Source checked: Oct 5, 2026
Owner-authorized agent editorial review (issue #120). The story was reorganized into sections and plain-language wording from this previously reviewed source. Added context sentences are supported by the supporting_source entries dated October 13, 2026.