A larger water main has been proposed for the Almond Garden affordable-housing redevelopment at 707–815 Almond Street in Suisun City. The Suisun-Solano Water Authority's September 14 staff report says the upgrade would meet the redevelopment's firefighting-water needs. The city reported housing construction underway September 1; today's stage remains unverified.
Proposed waterline upgrade
The Suisun-Solano Water Authority’s September 14, 2026 staff report proposed replacing the existing 6-inch main in Almond Street with a 10-inch main. Staff proposed that the authority reimburse 56% of eligible costs. Its estimated reimbursement was $204,478.74, including contingency; that figure was not the total construction cost.
Decision and work remain unverified
Minutes included in the October 5 Executive Committee packet record a September 8 recommendation for Board approval. A Board decision, signed reimbursement agreements and completed waterline work have not been verified in this review.
Housing details
The city’s August update describes a three-story project, with Planning Commission approval in January 2024 and an appeal denied by the City Council in March 2024.
City sources differ on the apartment count: a December 2024 release described 99 units, while the June 2025 notice and August 2026 update describe 97. The reviewed documents do not explain the difference.
Today’s construction stage, completion date and move-in availability remain unverified.
How we know (6 sources)
Dated source evidence; the project may have changed since then. An approval does not establish construction or an opening.
Supporting source
Packetp7 September8committee minutes record recommendation for Boardapproval; not proof of September14Boardadoption, executedagreements or completedwaterline.
SSWA October5 Executive Committee packetSuisun-Solano Water Authority · Retained original p7, committee role separate from Board
Evidence dated: Oct 5, 2026 · Source checked: Oct 22, 2026
Reviewed retained original/authorized rendered city source supports this dated claim; matched project parcels do not establish corporate succession, adoption or completed work.
Supporting source
The city's Sept. 1, 2026 release said construction is underway on the Almond Garden project.
Suisun City and California Forever Finalize First Phase of Downtown Property SaleCity of Suisun City · release, downtown projects list
Evidence dated: Sep 1, 2026 · Source checked: Oct 7, 2026
Owner-authorized agent evidence review under #25. City-stated facts as of the source date; later outcomes, openings and completion are not inferred. No human reviewer impersonated.
Supporting source
Citynotice identifies97-unit redevelopment at707–815AlmondStreet onbothAPNs0032-101-420 and0032-102-160; ties Septemberwaterlineproposal tosamehousingproject. Fundingrequestforecast is not fundingrelease.
Suisun City Housing Authority June26,2025 noticeCity of Suisun City Housing Authority · Authorized ordinaryChrome renderedHTML/AX retainedOctober22; originalHTTPresponse notobtained; paragraphidentifyingproject/APNs
Evidence dated: Jun 26, 2025 · Source checked: Oct 22, 2026
Reviewed retained original/authorized rendered city source supports this dated claim; matched project parcels do not establish corporate succession, adoption or completed work.
Supporting source
Dated city update: 97 affordable apartments at707–815AlmondStreet, three-story project; January2024PlanningCommissionapproval, appeal deniedMarch2024. No supported single-building count or currentcompletion claim.
Suisun City Infill Development Update, August4,2026City of Suisun City · Development slide7 and Council/Planning packetp8; singular-building wording corrected from prior summary
Evidence dated: Aug 4, 2026 · Source checked: Oct 22, 2026
Reviewed retained original/authorized rendered city source supports this dated claim; matched project parcels do not establish corporate succession, adoption or completed work.
Summary
Staff proposal: 6-inch to10-inch AlmondStreet water main for fireflow;56% eligible cost reimbursement, estimated$204478.74 including20% contingency, not totalconstructioncost. Both projectAPNs0032-101-420 and0032-102-160. Resolution26-14 fields blank; adoption/execution/payment/worknotverified. Later estimate supersedes Sept8preliminary estimate.
Suisun-Solano Water Authority September14,2026 Board packetSuisun-Solano Water Authority · Retained original pp19–22,41–42; hashes and reviewed renders in October22package
Evidence dated: Sep 14, 2026 · Source checked: Oct 22, 2026
Reviewed retained original/authorized rendered city source supports this dated claim; matched project parcels do not establish corporate succession, adoption or completed work.
Supporting source
December13,2024 cityrelease describes99 units; June2025notice andAugust2026cityupdate say97. No explanation/finalcount resolution established.
Almond Gardens Redevelopment funding approval city releaseCity of Suisun City · Authorized rendered cityHTML/AX retainedOctober22; apartmentcount paragraph; bodydiscloses97/99 difference
Evidence dated: Dec 13, 2024 · Source checked: Oct 22, 2026
Reviewed retained original/authorized rendered city source supports this dated claim; matched project parcels do not establish corporate succession, adoption or completed work.